|
Plumbing rough-in, forms and beams |
|
Post tension cables |
This is the 2nd installment of the house building chronicle: One of the requirements of building in
The Shores on Richland Chambers is the engineering process for your slab. We got the drawings and turned them over to the concrete contractor. He took them and got started forming and digging the grade beams. We selected a plumber after reviewing several bids and they came to rough in the slab. Once the plumber was done I called our local
Orkin franchise to 'pre-treat' the slab. They came out and sprayed really good stuff around all the plumbing openings in the concrete. This will seriously dissuade any bugs with the intention of coming inside form underneath. This is step one of their process. They will come back after the house is just about done and spray around the edge of the foundation.
|
Slab pre-treat |
|
Slab pre-treat |
|
Pump truck to place the concrete |
Once the pre-treat was done our concrete contractor came back and continued preparing the slab. They finished and reinforced the forms, laid plastic moisture barrier and placed the post tension cables along with some rebar. Early the next morning concrete trucks started to arrive. Since our lot is fairly narrow and the slab is pretty large a pump truck was necessary to place the concrete. All the concrete was poured at the same time for what is referred to as a 'monolithic' pour. Which simply means it is all one big piece.
|
The truck is controlled remotely |
|
Placing concrete |
|
Placing concrete |
|
Finished slab |
Once concrete is poured it is there. You have to think through everything that needs to go in the floor. I would have done a couple of thing differently at this point, nothing earth shaking, but definitely causing a little extra work to get accomplished now.
This post are so much useful to everyone.Just reading anyone clear it easily.I like it thanks for your sharing.
ReplyDeleterebar reinforcement